HET End-Trimester Report
Third Period of 2022
August 1 - November 30

This report is composed of five sections:
Facility Status

In this section we will discuss the status of the HET facility and each instrument and any limitation to configurations that occurred during the period.

                      
               

A Note to HPF Users from Suvrath and the HPF team:


On November 23rd the temperature of the HPF cold finger inside the instrument showed a sudden jump, with the cold finger warming up a fraction of a degree. The jump corresponds to a real change in the internal physical configuration of the HPF instrument- ie. it is not just a faulty sensor. Corresponding to this jump in the cold finger, the HPF bench immediately started to cool, with exponential decay, and has now cooled by almost 50milliKelvin, with the bench temperatures settling now. With HPF's typical stability at the millikelvin or sub millikelvin level, this is a sudden and steep change to normal operations. A jump in the output power of the wall heater closest to the cold finger has also been detected, temporally coincident with the jump in the cold finger temperature. The preferred hypothesis of the HPF team is that something physically changed that is now more strongly coupling the cold finger to the rest of the instrument. For example, a tear, or slip in the MLI covering the cold finger that leads to enhanced radiative coupling, or a physical contact that did not exist before.  Such an event has not happened in HPF before, in its multi-year operations. 


Approximately a week before this temperature transient occurred an earthquake was felt at the HET. The proximity of these events is suspicious, and tempting to attribute causality to. But no direct physical evidence yet exists in hand to definitively link these events. It is the HPF's team's current thinking that this is quite concerning, but does not yet rise to the level of needing an intrusive multimonth instrument takedown, and does not currently seem to be threatening the instrument itself. If temperatures settle and stabilize, HPF stability, with calibration, should be similar to before. The transient and large nature of this event though means that calibration is unlikely to work perfectly for some days after the event started. We have not looked at the on-sky velocities pre and post this event yet, so there remains the possibility that the event may cause an uncalibrated jump in the RVs, especially in cases where simultaneous calibration is not used, and the processing relies on the underlying smoothness and stability of the HPF drifts. This event breaches the assumptions of slow drifts and smoothness built into the HPF drift models in the HPF pipeline.  


In summary- we have a plausible physical explanation of what might have happened, that fits all the available telemetry data, but not incontrovertible proof. A detailed root-cause analysis of this event is therefore not currently envisioned, since this will require intrusive instrument takedown, and a concomitant loss of astrophysics.  Monitoring of this situation is ongoing.







Probe and instrument availability statistics:
There were a total of 123 nights in the trimester:
LRS2-B
LRS2-R
VIRUS
HPF
HPF
LFC
HPF
high-prec.
Guider 1
Guider 2
WFS 1
WFS 2
DIMM
123
123
123
123
123
120
119
119
111
115
123
100%
100% 100% 100%
100%
98%
97% 97% 90%
93% 100%




Observing Statistics

Commissioning, Engineering, and Guaranteed Time Report There were 224 hours granted in the 22-3 period:

There were 185.2 hours of eng/comm/GTO used (charged) in the 22-3 period, in the following categories:





Month by Month Summary

The following table gives the observing statistics for each month. Column A gives the fraction of the month that was spent attempting science (as opposed to engineering or instrument commissioning). Science time is defined to begin at 18 degree evening twilight and end at 18 degree morning twilight. Column B gives the fraction of the possible science time (A) lost due to weather. The other columns give the amount of remaining science time (after removing weather losses) not spent attempting science targets. Please note that the first stack of the night often occurs before 18 degree twilight.

Month A:
Fraction of the Time that was Possible Science
B:
Fraction of Total Time Lost due to Weather
C:
Fraction of Actual Science Time Spent with Shutter Open
D:
Fraction of Actual Science Time Lost due to Overhead
E:
Fraction of Actual Science Time Lost due to Alignment
F:
Fraction of Actual Science Time Lost due to Problems
G:
Fraction of Actual Science Time Not accounted for or Lost
Aug
0.846
0.576
0.565
0.226
0.0939
0.1150
0.0000
Sep
0.984
0.332
0.649
0.251
0.0447
0.0549
0.0000
Oct 0.991
0.466
0.648
0.250
0.0662
0.0351
0.0000
Nov
0.986
0.506
0.621
0.256
0.0747
0.0483
0.0000

The following tables give a break down of all attempted science visits as well as the category that each falls into.

Charged exposures
Number of Times Shutter Open (Hours) Type
3471
463.85
A - Acceptable
131
27.02
B - Acceptable but Border line conditions
122
25.78
4 - Priority 4 visits (does not include 1/2 charge)
0
0.0 Q - charged but PI error
0 0.0 C - Acceptable by RA but PI rejects

Uncharged exposures caught by RA
Number of Times Shutter Open (Hours) Type
2
0.58
N - Rejected due to unknown cause
53
8.58
E - Rejected for Equipment Failure
365
74.42
W - Rejected for Weather
9
2.80
H - Rejected for Human Errors

Uncharged exposures caught by PI
Number of Times Shutter Open (Hours) Type
4
1.33
P - Rejected for weather
6
2.47 F - Rejected for Equipment Failure
0
0.00 T - Rejected for poor track choice
0
0.00 X - Rejected for Human Errors

Acceptable but Uncharged exposures
Number of Times Shutter Open (Hours) Type
0
0.0 I - Targets observed under otherwise idle conditions

The following setup statistics include slew, acquisition, and starting data collection script. The table below gives the average setup time for each instrument PER ACTUAL VISIT and the average and maximum COMPLETED charged science exposures and visits.

The "Exposure" is defined by when the (CCD) shutter opens and closes. A "Visit" is the requested total CCD shutter open time during a track and might be made up of several "Exposures". "Visit" as defined here contains no overhead. To calculate one type of observing efficiency metric one might divide the "Visit" by the sum of "Visit" + "Overhead".

The average setup per visit is calculated from acceptable priority 0-3 (not borderline) science targets. This number reflects how quickly we can move from object to object on average for each instrument, however, this statistic tends to weight the setup for programs with large number of targets.

The average overhead percentage is calculated for each instrument and shows how much of that instrument's total time on sky (overhead+exposure) was overhead. NB: LRS2 has the smallest overhead %, but typical LRS2 observations use much longer exposures than VIRUS, even though VIRUS has a faster average setup time.



Instrument Avg Setup per Visit
(min)
Total time exposed
(hrs)
Overhead
%
VIRUS 4.59
114.48
41.52%
LRS2 6.17
64.33
33.47%
HPF 6.55
176.92
28.02%

The setup statistics can be shortened by multiple setups (each one counted as a separate visit) while on the same target such as moving from LRS2-B to LRS2-R.



HETDEX time interruptions:

Within the times when HETDEX shots were available on-sky for >20 minutes, the following percentages summarize how the time was used:




Overall time charged: 185.2 (eng/comm/GTO) + 356.7h (sci) = 541.9h
Total estimated science time available (in TAC time determinations): 624.2h
   Conclusion: weather in 22-3 was much worse than expectations...
      The past two 3rd trimesters charged times were 620.8h and 707.3h, so this one had exceptionally poor weather



Observing Programs Status

In the table below we show the breakdown of the charged time for each program submitted. The "Total %" is the completion of the entire TAC time including P4 time. The last four columns show the completion rate for targets submitted in each priority bin. This completion rate is the greater of the targets completed percentage and the TAC allocation completed percentage in each priority bin.

Institution Tot exp
Tot OH
Tot Chrg Tot TAC Total % P0 Completion
P1 Completion P2 Completion P3 Completion










G22-3-001 0.22
0.10
0.32
0.33
96%


100%
G22-3-002 10.50
2.53
13.03
15.27
85%
100%
100%
100% 63%










M22-3-001 0.82
0.17 0.98
7.00
14%

35%
0% (SI)

M22-3-002 2.25
0.68
2.93
6.00
49%
100%
55%
0% (SI)

M22-3-003 1.47
0.43
1.90
2.00
95%
100%



M22-3-004 11.25
6.08
17.33
17.20
101%


100%
100%










PSU22-3-001 0.71
0.00
0.71
1.33
53%(P4)



100%
PSU22-3-002 1.97
0.50
2.47
3.65
68%

100%
33%

PSU22-3-003 3.83 1.48
5.32 5.20 102%
100%
100%


PSU22-3-004 13.39
3.30
16.68
22.39
75%(P4)


100%
91%
PSU22-3-005 0.09
0.13
0.22
0.26
83%


100%

PSU22-3-006 0.68
0.00
0.68
6.33
11%(P4)




PSU22-3-007 1.50
0.37 1.87 3.62
52%


52%
PSU22-3-008 J*
J* J* J* J* J* J* J* J*
PSU22-3-009 7.56
1.75 9.32 10.67
87%
81%
91%

PSU22-3-010 32.03
8.04
40.07
39.99
100%
100%
100%
100%
100%
PSU22-3-011 0.00
0.00
0.00
0.00
0%

0% (TD)












UT22-3-001 9.34
3.73
13.07
16.00
82%
100%
100%


UT22-3-002 5.83
1.18
7.02
12.50
56%(P4)


86% (TD)
71% (TD)
UT22-3-003 15.30
8.25
23.55
35.90
66%(P4)

93%
76%

UT22-3-004 3.83 1.08
4.92
5.50
89%
89% (DT)



UT22-3-005 4.67
0.88
5.55
7.30
76%

100%
75%

UT22-3-006 6.50
3.38
9.88
14.00
71%

89%
63%

UT22-3-007 7.30
2.40
9.70
10.00
97%
93% (DT)
100%


UT22-3-008 J*
J* J* J* J* J* J* J* J*
UT22-3-009 13.90
9.14
23.04
35.00
66%(P4)
93%
100%
95%
78%
UT22-3-010 9.97
8.82
18.78
39.00
48%(P4)


96%
61%
UT22-3-011 4.83
1.03
5.87
5.00
117%

100%


UT22-3-012 3.19
0.51
3.70
22.00
17%(P4)


75%
0% (DT)
UT22-3-013 2.92
0.57
3.48
10.00
35%


35% (DT)

UT22-3-014 2.50
0.47
2.97
7.00
42%

58% (DT)


UT22-3-015 33.08
7.80 40.88
50.00
82%(P4)

94%
100%
100%
UT22-3-016 11.11
9.52
20.63
32.50
63%(P4)


100%
84%










HET22-3-100 85.40
27.45
112.85
160.00 70.53%
71%



HET22-3-203 2.33
0.53
2.87
6.00
48%
83%
80%
0% (DT)
0% (DT)
HET22-3-300 16.01
3.75
19.76
20.00
99%
100%
100%
100%





















UT22-3-008
+PSU22-3-008
41.24
8.73
49.97
58.00
86%(P4)

100%
88%
100%




















J* = joint program between UT, PSU, and Munich - see summary at bottom of table
NT = no (or very late-in-trimester) targets submitted at this priority (even though time was allocated)
HC = HETDEX conflict (targets submitted were in direct competition with HETDEX; PI was aware of issue)
SI = Seasonally inappropriate or narrowly distributed target list
TD = Time Domain targets (either none submitted or submitted targets unreachable due to weather)
DT = Dark Time targets (or grey time; often need high priority and good sky distribution to be successful)
P4 = Program's overall completion fraction is significantly impacted by the utilization of P4 time


Program Completion Rates
(sci only, removing NT/HC/SI/TD)
Priority Average Completion Median Completion
P0 94.1% 100%
P1 88.7% 100%
P2 81.4% 95%
P3 71.5% 84%

Special note for 22-3:
 While these percentages are lower than most trimesters, they were driven in part by a number of small programs (many dark time or single-target programs) achieving 0% completion rates at a given priority. The table below shows the numbers of hours allocated and charged at each priority, to give a different perspective:
(UT+PSU+G+M; not including HET GTO programs)

hours allocated
hours charged
P0
33.63
31.84 (94.7%)
P1
105.15
93.18 (88.6%)
P2
140.35
113.09 (80.6%)
P3
135.40
111.55 (82.4%)




Completion trends by priority









Institution Status

Below we show how the TAC allocations were determined.

quantity
Aug
(hrs)
Sep
(hrs)
Oct
(hrs)
Nov
(hrs)
Total
(hrs)
18deg-18deg
243.93
268.10
306.58
318.17
1136.78
Weather loss frac. 0.44
0.48
0.36
0.37

Efficiency loss frac.
(align+PRs)
0.08
0.07
0.07
0.07

"Clear science" time
125.67
129.65
182.48
186.41
624.22
Com/Eng/GTO time
(estimated)




209.00
"Allowed" hours
given to TACs
for science




415.22




Partner
Share
Time deficit correction
Notes
Total hours
allowed
Goettingen
0.03860
-0.45

15.58
Munich
0.05724
+5.79

29.56
PSU
0.24897
-6.57

96.81
UT
0.65518
+1.23
-10h TESLA allocation
   per HET Board
263.27

Corrections were applied using 20% of the cumulative deficits in time balance between the partners. As of May 15th 2022, those time deficits were:
  UT:   4.1h deficit
  PSU: 21.9h surplus
  M:    19.3h deficit
  G:     1.5h surplus
Actual time usage is carefully monitored to ensure equitable balance between the partners; these corrected allocations should help improve this balance over the long-term.

TACs may allocate up to 8.3% at P0, 25% at P1, 33.3% at P2 and 33.3% at P3. P4 allocations are generally un-restricted. GTO and engineering time are assigned by the HET board and not from this formula.
(Note that in 23-1 the division between P0 and P1 time has changed! see the Beginning of Trimester report for 23-1 for more details.)


This is how each institution had allocated its time by priority:

Time Allocation by Institution (hours)

Institution Priority 0 Priority 1 Priority 2 Priority 3 Priority 4 Total P0-P3
Frac. of allowed
Goettingen 1.30
3.90
5.20
5.20
-
15.60
100.1%
Munich 2.50
7.30
12.50
9.90
-
32.20
108.9%
PSU 7.33
24.10
32.30
32.30
12.41
96.03
99.2%
UT 22.50
69.85
90.35
88.00
75.00
270.7
102.8%
Other allocations
GTO 166.00 10.00 9.00 1.00
-
186.00
100.0%

Notes:
1) Allocations in joint programs are reported separately for each partner here





The following is a summary of the total charged time for each institution based on our htopx data base (for shutter open) and night reports (for overhead). It includes shutter open time (weighting priority four by half) and overhead (no overhead for priority 4 observations). Recently this calculation was re-derived using a deficit/surplus model. For each financial year the share paid is compared with the time charged - any discrepancy between the two is tracked and carried forward as a deficit. A negative deficit means more time was observed for that partner than their financial share; a positive deficit means less time was observed. These deficits are calculated in each previous financial year; the table below also includes a preliminary total for the current financial year so far.

Accumulated deficits
for each partner


UT
PSU
M
G
total sci
hours
FY2015-2016

+4.6
-6.9
+1.1
+1.2
40.49
FY2016-2017

+22.7
-22.8
+0.8
-0.8
439.56
FY2017-2018

+37.7
-21.9
-14.7
-1.2
887.71
FY2018-2019

+43.0
-32.0
-10.8
-0.2
1401.17
FY2019-2020

+48.9
-48.4
+0.6
-1.1
2101.82
FY2020-2021

+25.1
-37.6
+13.8
-1.3
3095.70
FY2021-2022

+1.7
-19.0
+13.5
+3.8
4140.40
FY2022-2023 (as of 1-Dec)

+6.6
-21.5
+10.7
+4.2
4497.10
percent of deficit:

+0.15%
-0.48%
+0.24%
+0.09%

*Note that UT's deficit is decreasing and all partner deficits are <0.5% of total science hours since the WFU.
NB: a more comprehensive annual partner fractional time charging analysis is produced separately from these trimester reports; a current copy can be provided upon request.



Below are the summaries of the Guaranteed Time Observations (GTO) programs granted by the Board:

GTO and Special Time Charged by Project (hours)
Project Allocated
in 22-3
Allocated total
to date
including 22-3
Charged
in 22-3
Charged total
to date
including 22-3
HETDEX (HETYY-P-100) 2894.0 2704.0 112.9
2184.3
LRS2 GTO (HETYY-P-2XX) 6.0 205.9 2.9
127.4
HPF GTO (HETYY-P-3XX) 20.0 260.4 19.8
261.1
GW (HETYY-P-400) 0.0 70.0
0.0
12.4

(Totals to date start from the 11-2 period)






Significant time losses to problems during the trimester

The following are our most significant problems in terms of their time lost, keeping those with >60min lost:

Lifetime
science
time
lost
hh:mm
PR #
Brief description
04:43
6027
6097
SAMS -384 issues, electronics/sensor related
04:00
4239
DMI returning 9999, fiber cleaned and replaced
02:43
4683
5685
"Failed to send point to TMCS" or "TMCS lost trajectory" errors
02:09
6096
Tracker oscillation; loose 1 second pulse cable
02:08
6100
GPS time stamp corruption results in tracker hitting soft limits and small skew
01:28
5364
6080
probe move timeouts and other issues
01:26
6074
HPF TIMS client crash, loss of metadata
01:18
4776
Dome stops at wrong position
01:09
6120
DSpace issue, replaced DS1005 board









SJ, 13 Dec 2022